Kanadevia Inova Steinmüller for GML – Boiler pressure test successful

With the successful “boiler pressure test” of the new waste boiler 4 on September 23, 2021, GML and Kanadevia Inova Steinmüller reach the next milestone of the GML modernization project IGNIS on time. From mid-April to mid-September 2021, Kanadevia Inova Steinmüller, together with the installation company Đuro Đaković, assembled the new K4 waste boiler on behalf of GML in the course of just five months.

“The last five months were challenging and very exciting for all involved! We would like to thank the fitters and welders as well as the installation management of Kanadevia Inova Steinmüller and Đuro Đaković very much for this outstanding performance!”

– GML Supervisory Board Chairman Alexander Thewalt & Managing Director Dr. Thomas Grommes

 

The successful boiler pressure test was celebrated accordingly by Kanadevia Inova Steinmüller and GML.

The original press release by GML can be found here:  https://www.gml-ludwigshafen.de/presse/kesseldruckprobe-erfolgreich

Images by GML via https://www.gml-ludwigshafen.de/presse/kesseldruckprobe-erfolgreich